Question 39 of 44intermediate🔧 ApplyShort Answer4 marks

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹ 200 for the first day, ₹ 250 for the second day, ₹ 300 for the third day, etc., the penalty for each succeeding day being ₹ 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Correct Answer

The contractor has to pay ₹ 27,750 as penalty.

Exercise: EXERCISE 5.3 | Q: 15 | (Page Page 21)
For More Understanding

Explanation

This question is from the Arithmetic Progression chapter. The penalties for each day form an AP with first term ₹ 200 and common difference ₹ 50. The total penalty is the sum of first 30 terms of this AP, which can be calculated using the sum formula S_n = n/2 × [2a + (n-1)d].

Solution Steps

  1. Identify the AP parameters: The penalty for first day = ₹ 200, so first term a = 200. Each succeeding day penalty is ₹ 50 more than preceding day, so common difference d = 50. Number of days delayed n = 30.

  2. Apply the sum formula: The total penalty is the sum of first 30 terms of this AP. Using formula: S_n = n/2 × [2a + (n-1)d]

  3. Substitute values: S_30 = 30/2 × [2(200) + (30-1)(50)]

  4. Calculate: S_30 = 15 × [400 + 29×5029 \times 50] = 15 × [400 + 1450] = 15×185015 \times 1850 = ₹ 27,750