Question 28 of 31advanced🔧 ApplyNumerical5 marks

A firm’s SMC schedule is shown in the following table. The total fixed cost of the firm is Rs 100. Find the TVC, TC, AVC and SMC schedules of the firm.

QQTC
0-
1500
2300
3200
4300
5500
6800
Correct Answer

Given: TFC = Rs 100, and the table shows SMC schedule.

Step 1: Calculate TC Schedule At Q=0, TC = TFC = Rs 100 (since TVC = 0 at zero output) TC at each level = TC at previous level + SMC

TC at Q=1 = 100 + 500 = Rs 600 TC at Q=2 = 600 + 300 = Rs 900 TC at Q=3 = 900 + 200 = Rs 1100 TC at Q=4 = 1100 + 300 = Rs 1400 TC at Q=5 = 1400 + 500 = Rs 1900 TC at Q=6 = 1900 + 800 = Rs 2700

Step 2: Calculate TVC Schedule TVC = TC – TFC

TVC at Q=0 = 100 – 100 = Rs 0 TVC at Q=1 = 600 – 100 = Rs 500 TVC at Q=2 = 900 – 100 = Rs 800 TVC at Q=3 = 1100 – 100 = Rs 1000 TVC at Q=4 = 1400 – 100 = Rs 1300 TVC at Q=5 = 1900 – 100 = Rs 1800 TVC at Q=6 = 2700 – 100 = Rs 2600

Step 3: Calculate AVC Schedule AVC = TVC ÷ Q

AVC at Q=1 = 500 ÷ 1 = Rs 500 AVC at Q=2 = 800 ÷ 2 = Rs 400 AVC at Q=3 = 1000 ÷ 3 = Rs 333.33 AVC at Q=4 = 1300 ÷ 4 = Rs 325 AVC at Q=5 = 1800 ÷ 5 = Rs 360 AVC at Q=6 = 2600 ÷ 6 = Rs 433.33

Complete Schedule Table:

QSMC (Rs)TC (Rs)TVC (Rs)AVC (Rs)
0–1000–
1500600500500
2300900800400
320011001000333.33
430014001300325
550019001800360
680027002600433.33
Exercise: EXERCISES | Q: 27 | (Page 17)
For More Understanding

Explanation

The question provides the SMC schedule (though labeled as TC in the table header, the question text clarifies it shows SMC). Using the relationship SMC = ΔTC/Δq, we can derive TC by cumulatively adding SMC to the previous TC. Starting from Q=0 where TC equals TFC (Rs 100), each subsequent TC is calculated. TVC is derived using TVC = TC – TFC, and AVC using AVC = TVC/q. The AVC first falls (from Rs 500 to Rs 325 at Q=4) and then rises, showing the typical U-shaped AVC curve.

Solution Steps

  1. Step 1: Identify that the table shows SMC values, and at Q=0, TC = TFC = Rs 100

  2. Step 2: Calculate TC at each output level using TC(n) = TC(n-1) + SMC(n)

  3. Step 3: Calculate TVC at each level using TVC = TC – TFC

  4. Step 4: Calculate AVC at each level using AVC = TVC ÷ Q

  5. Step 5: Present all schedules in a complete table format